The construction work of main lines destressing of Chang- Zhu-Tan Intercity Railway was completed on July 28, 2016, making another major success after long rail laying on June 13.
Later as scheduled tight alignment and tamper in Changsha section and Zhuzhou section are expected to be finished by the end of August, to make sure joint debugging of the whole line in mid-September.
The construction of Chang- Zhu-Tan Intercity Railway is undertaken by China Railway 25th Bureau Group.